Westlake Approved a Data Center About 500 Feet From Keller Backyards. The Zoning Vote That Made It P
Westlake, Texas — Nov. 16, 2026.
On Thursday, Nov. 12, the Westlake Town Council approved the development agreement for the Circle T data center, an approximately 87.96-acre site at the northeast corner of U.S. 377 and Westport Parkway. The Fort Worth Report says the vote was 5-1. Council also signed off on the settlement that ended a lawsuit from the Keller neighborhood next door.
Most of the coverage has been about noise and lawsuits. Fair enough. But if you own land, the lessons are somewhere else. The vote that actually made this project possible happened on Jan. 6, 2025, when Westlake adopted "text amendments" to the site's zoning that made a data center a by-right use and raised the height limit from two stories or 35 feet to 80 feet. Nobody spoke at that hearing. And the deal approved Thursday has a trapdoor in it: no final certificate of occupancy until the developer shows it cleared a state grid audit that the incoming governor has said she wants to replace with a moratorium on data center approvals.
Location (approximate): U.S. 377 and Westport Parkway, Westlake. The site is on the east side of U.S. 377, inside Westlake, and Keller's Lakes at Marshall Ridge neighborhood runs along its southern property line.
What Westlake approved
Two items, both at a Nov. 12 special meeting:
The settlement (Resolution 26-35). It authorizes the town manager to sign settlement agreements with the Lakes at Marshall Ridge Homeowners Association, three named residents and the City of Keller, plus a mutual aid agreement with Keller. It also approves a deal requiring Circle T to reimburse Westlake's attorneys' fees and public relations costs from the lawsuit. It was on the consent agenda. The Fort Worth Report says it passed unanimously.
The development agreement (Resolution 26-36) with Circle T Owner, LP. This item was tabled on Aug. 17. Westlake's own recap says council approved it "as presented" after public comment for and against. Per the Fort Worth Report, Council Member Michael Yackira cast the lone no vote.
The lawsuit was Cause No. 342-381199-26, filed by the HOA and residents Linda Bjorn, Sharon Sanden and Kevin Myers against the town, the mayor and council members. Keller joined it, per the Fort Worth Report, which also says a Fort Worth district judge's temporary restraining order barred council from moving forward with the August approval. CBS Texas reports the order was later dissolved.
Who's building it: news reports identify the developer as PowerHouse Data Centers. NBC 5 says the plan is four buildings totaling about 1.1 million square feet. The agreement itself is with Circle T Owner, LP, which WFAA describes as the property's legal owner.
The zoning vote nobody spoke at
Here's the part I'd underline. The Nov. 12 vote wasn't a zoning vote. Under Westlake's code, a development agreement is required before construction permits on platted land and planned development zoning, so that's the vote everybody fought over. The zoning was already in place.
The site is in PD, Planned Development District 3-8, Office/Industrial Sub-District. The district was created by Ordinance No. 314 on Sept. 14, 1998, and amended in 1998, 2003 and 2008. Westlake's position, as quoted by the Fort Worth Report, is that the land has been zoned for commercial and industrial use since 1998: "An industrial or commercial project like a data center, a large distribution center, or something similar was always expected, hence why our zoning hasn't changed in 28 years." The town also says the Keller land next door was zoned for commercial and industrial use until 2006, when Keller changed it to residential.
The district has been there since 1998. But the rules that fit this project are newer. On Jan. 6, 2025, the Town Council adopted Ordinance No. 1015. The agenda called it "text amendments to PD, Planned Development District No. 3-8," and the words "data center" weren't in the agenda caption. Per the town's staff report, the amendments:
Made a data center permitted by right in the Office/Industrial sub-area (and by specific use permit in the Office sub-area). The ordinance adds a note that after site plans are submitted for the first data center in the Office/Industrial sub-district, "each successive data center thereafter shall require a SUP."
Raised the maximum height in Office/Industrial to 80 feet from two stories or 35 feet.
Replaced the 0.30:1 floor-area ratio with 70% lot coverage for Office/Industrial.
Made electrical substations by right instead of by specific use permit.
Replaced the old residential slope rule (no non-single-family structure taller than a 5:1 line drawn from any single-family lot line) with "a Minimum 150 foot setback required between a single family, detached residential use and non-commercial uses," plus a landscaped buffer yard approved by council with the site plan.
The staff summary doesn't say what the pre-2025 rule for data centers was. An opposition website says the 1998 use table didn't allow them at all. I couldn't confirm that from a clean copy of the 1998 table, so I'm not saying it as fact.
The minutes from Jan. 6, 2025: the mayor opened the public hearing, "There was no one to speak," and the ordinance passed unanimously with one council member absent. The second on that motion was Council Member Michael Yackira, the same member who voted no on Thursday. The Planning and Zoning Commission had recommended approval 5-1-1 on Dec. 10, 2024. From there it went: site plan approved with conditions on Aug. 4, 2026, development agreement tabled Aug. 17, approved Nov. 12.
Compare that with Prosper. In September, White Rose Partners wanted to rezone 37.3 acres at FM 1385 and Parvin Road from agricultural to a planned development for a data center called Project Tomahawk. Prosper's Planning and Zoning Commission recommended denial 7-0 on Sept. 1 after more than an hour of opposition, and the developer withdrew before the Sept. 8 council meeting, according to Community Impact. Same type of use, though Prosper's was much smaller (about 225,000 square feet, per town staff as reported by Community Impact). In Prosper, the zoning hearing drew more than an hour of opposition and the project died. In Westlake, the zoning hearing was empty, and the fight didn't start until Westlake announced the project online on July 29, 2026, according to the Fort Worth Report. That was 19 months after the zoning change and less than a week before the site plan was approved.
Map: Ixnayonthetimmay / Wikimedia Commons, public domain. Incorporated areas of Tarrant County, with Westlake highlighted in red (2007 map; city limits may have changed since).
What's in the development agreement
Straight from the agreement and the town's staff report in the Nov. 12 packet:
No state sign-off, no final CO. The town won't issue a final certificate of occupancy for any building until the developer hands over documents confirming it has complied with the Public Utility Commission of Texas and ERCOT requirements tied to Gov. Greg Abbott's Aug. 3, 2026 directive on data center audits. If the developer builds and doesn't get those approvals by the final certificate of occupancy, the town manager "may request" that the developer repurpose the buildings for another use the zoning allows. If the developer decides not to pursue the approvals, it doesn't have to build at all.
Water. The town agrees to make 692,000 gallons per day of water and 231,000 gallons per day of sewer capacity available by Oct. 1, 2027, rising to 1.5 million gallons per day of water and 500,000 of sewer by July 1, 2028. The agreement puts anticipated water use at about 54 million gallons a year. My math: that's an average of roughly 148,000 gallons a day, about a tenth of the reserved capacity. The agreement doesn't explain the gap. Cooling has to be designed for a water usage effectiveness of no more than 0.25 liters per kilowatt-hour as a long-term average. The agreement estimates the system will run without water for cooling about 85% of the year, but says those numbers are estimates, not guarantees. Hillwood Alliance Services, LLC is designing and building the public water and wastewater extensions to the site.
$914,000 for the pump station. A one-time cash contribution of up to $914,000 to upgrade piping at the town's pump station, due within 30 days of signing. Staff says the agreement doesn't waive, reduce or defer any development fees.
Power. Oncor is responsible for the switchyard and other facilities to bring service to the property. The developer designs and builds the on-site substation and private electrical infrastructure. The Fort Worth Report says the developer paid Oncor to build a 350-megawatt substation on the west side of town.
Berm and trees. A 10-foot berm along the part of the southern property line closest to Lakes at Marshall Ridge, tapering on either side. A continuous screen of container-grown evergreen and hardwood trees, at least 3-inch caliper at planting, more than half evergreens, with dedicated irrigation.
Noise. A baseline noise study before construction. Then, within 180 days after the last building is finished, quarterly reports for one year showing compliance with Westlake's noise code, measured in dBA and across octave bands, including low-frequency sound. The code table in the agreement lists 56 on the A scale "for monitoring purposes only," with 7 dB subtracted for nighttime noise between 7 p.m. and 7 a.m.
Looks. At least 50% natural stone on accessory buildings, rooftop equipment screened by walls at least 12 inches taller than the equipment, and stone retaining and screening walls.
Photo: Z22 / Wikimedia Commons, CC BY-SA 4.0. Henson Data Center in Dallas, Sept. 24, 2024. Example of an existing DFW data center, not the Circle T project.
What Keller got
I couldn't pull Keller's settlement document directly; the city's website blocked my download. So this section relies on Keller's announcement as reported by CBS Texas, NBC 5 and WFAA.
According to those reports, the settlement was signed Nov. 5 and requires the developer to pay $1.876 million within 45 days: $1.5 million for a noise mitigation fund, $300,000 for Keller Fire-Rescue and $76,000 for Keller's legal and consulting costs. Noise is capped at 56 decibels during the day and 49 at night (7 p.m. to 7 a.m.), measured at residential property lines. Monitoring runs quarterly for three years after operations begin, not one. Diesel backup generators need EPA Tier 4 emissions controls, with testing limited to 10 a.m. to 4 p.m. CBS reports Keller says it gets contractual rights to enforce certain noise, screening and operating requirements outside its city limits.
Westlake reads it a little differently. Its staff report says the town "has not given away any enforcement rights to development in our town and has not agreed to allow another municipality to enforce our or other ordinances/requirements within town limits." Both can be true if Keller's rights run through its contract with the developer rather than through Westlake's ordinances, but I haven't seen the settlement text, so I'm not going to tell you how a judge would read it.
What Westlake gets: about $5 million a year in revenue for the first 10 years, rising to an estimated $7 million after that, according to the town. Westlake also says all settlement payments come from the developer, and its attorneys' fees were fully reimbursed.
Photo: 1958publius / Wikimedia Commons, CC BY-SA 4.0. Keller City Hall, July 11, 2015. Area photo; not the data center site.
The Austin wildcard
The certificate of occupancy condition ties this project to state policy, and state policy is moving.
Abbott's Aug. 3 letter, attached to the agreement, told the PUC and ERCOT to audit every data center in the interconnection queue "before any additional data centers are approved to move forward." The letter says ERCOT is considering about 474 gigawatts of requests to connect, more than five times the grid's record peak demand, and that about 90% of the new requests are data centers. It also tells regulators to collect what each project gets in tax incentives, whether it brings its own power and water, and what it's doing about noise, light and setbacks for its neighbors.
Then the election happened. The Texas Tribune reports that Democrat Gina Hinojosa won the governor's race on Nov. 3, takes office Jan. 19, and campaigned on a moratorium on all data center approvals until the Legislature passes new protections. The Tribune also reports the current audit was expected to last until December.
What that means for Circle T, I can't tell you yet. The agreement is written around whatever "guidelines, requirements, or processes" the PUC and ERCOT set, so it will follow the rules wherever they land. A longer pause would push the timeline. Changed rules could change the project. Nobody's said either one yet.
What it means for land
1. Read the "text amendments." The change that made this project possible went out as text amendments to an existing PD, and nobody spoke at the hearing. If you own a home or land next to a big tract with old commercial or industrial zoning, the agenda caption won't always say "data center." Pull the staff report on any amendment to the district next door, and look at the height, coverage, setback and permitted-use changes.
2. Entitlements already in place are the scarce thing. Prosper's Project Tomahawk needed an ag-to-PD rezoning and didn't survive its first hearing. I'd expect plenty of North Texas suburbs to be just as tough on rezonings for data centers for a while. Land that already allows the use, with power capacity nearby, is a lot harder to find. One more wrinkle in Westlake: under Ordinance 1015, only the first data center in the Office/Industrial sub-district is by right. The next one needs a specific use permit.
3. Price the neighbor fight into the deal. The Keller settlement alone is $1.876 million, before the berm, the trees, the noise studies, the pump station money, and the nearly three months between the tabled Aug. 17 vote and Thursday's approval. If you're selling land to a data center user next to homes, expect buyers to underwrite that, and maybe ask for a longer due diligence period or a closing tied to approvals.
4. Water and power still decide the site. This deal reserves up to 1.5 million gallons a day of water and depends on an Oncor switchyard and an on-site substation. A site without that kind of capacity nearby is a much harder sell, whatever the zoning says.
5. Watch Austin before you sign. With a CO tied to state approvals and a new governor promising a moratorium, any data center land contract written in the next few months needs serious thought about timing and what happens if the state slams the brakes. Talk to your lawyer about those contingencies before you sign.
What's next
Under the agreement, the $914,000 pump station payment is due within 30 days of signing. Per the news reports, the $1.876 million settlement payment is due within 45 days of the Nov. 5 settlement. The baseline noise study has to happen before construction. Then watch the PUC and ERCOT audit, and what the new governor does after Jan. 19.
If you own land near a big commercial or industrial tract and want to know what's actually allowed next door, or you're getting calls from data center buyers, email me at Dan@CooperLandCompany.com or visit cooperlandcompany.com.
Related reading
The 'Data Center' Dividend: Why High-Voltage Power is the New 'Frontage'
Water Rights: The 'Hidden' Asset in North Texas Land Deals
Plano Has 1,848 Apartments on Monday's Agenda. The Bigger Story Is Who Gets to Keep the Pipe Capacity.
Infrastructure Lag
Sources
Town of Westlake, Nov. 12, 2026 special meeting agenda (Items D.1 and E.1): https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=5541,plainText=false)
Town of Westlake, Nov. 12, 2026 special meeting agenda packet (staff reports, Resolutions 26-35 and 26-36, development agreement, Exhibit B approved plans and renderings, Exhibit C governor's letter): https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=5542,plainText=false)
Town of Westlake, "Town Council Recap (11-12-2026)": http://www.westlake-tx.org/m/newsflash/Home/Detail/840
Town of Westlake, "Data Center Settlement Details" (Nov. 6, 2026): http://www.westlake-tx.org/m/newsflash/Home/Detail/837
Town of Westlake, Aug. 17, 2026 special meeting agenda: https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=5484,plainText=false)
Town of Westlake, Jan. 6, 2025 Town Council agenda (Item F.2, Ordinance 1015): https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=104,plainText=false)
Town of Westlake, Jan. 6, 2025 agenda packet (staff report and Ordinance No. 1015): https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=62,plainText=false)
Town of Westlake, Jan. 6, 2025 Town Council minutes: https://westlaketx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=93,plainText=false)
Gov. Greg Abbott, letter to the PUC and ERCOT, Aug. 3, 2026 (Exhibit C in the Nov. 12 packet, source 2)
Fort Worth Report, "Westlake data center bordering Keller neighborhood moves forward after months of litigation" (Nov. 13, 2026): https://fortworthreport.org/2026/11/13/westlake-data-center-bordering-keller-neighborhood-moves-forward-after-months-of-litigation/
NBC 5 Dallas-Fort Worth, "Westlake approves development agreement for proposed data center" (Nov. 13, 2026): https://www.nbcdfw.com/news/local/westlake-approves-development-agreement-for-proposed-data-center/4105605/
WFAA, "Westlake OKs data center after settlement ends Keller neighbors' lawsuit" (Nov. 12, 2026): https://www.wfaa.com/article/news/local/tarrant-county/westlake-oks-data-center-after-settlement-ends-keller-neighbors-lawsuit/287-3c6a46e0-abaf-4f4b-9d5b-e543135e2002
CBS Texas, "Keller reaches settlement over Westlake data center, secures protections for nearby residents, city says" (Nov. 5, 2026): https://www.cbsnews.com/texas/news/keller-westlake-data-center-settlement-neighborhood-protections-november-2026/
CBS Texas, "Westlake approves agreement, clearing way for controversial North Texas data center" (Nov. 12, 2026): https://www.cbsnews.com/texas/news/westlake-data-center-approved-keller-settlement-noise-restrictions-november-2026/
Community Impact, "Project Tomahawk developer scraps plans for Prosper data center" (Sept. 8, 2026): https://communityimpact.com/prosper-celina/government/project-tomahawk-developer-scraps-plans-for-prosper-data-center/
The Texas Tribune, "Gina Hinojosa won the governor's race. What happens to Texas data centers now?" (Nov. 4, 2026): https://www.texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/
This article is general information, not legal or investment advice.